Programmes are among the most sensitive documents in a project. Planning locally keeps baseline logic, float and resource assumptions away from third-party servers.
The programme matters contractually only when it is consistent with the contract: milestones, access dates and the logic the other party has approved.
Before you adopt it
- Keep the approved baseline separate from working updates.
- Check that the export opens correctly in the format the contract requires.
- Record every logic change with a date and a reason.